Interior Design Checklist: Everything to Do Before, During & After Your Pune Project

You're about to invest ₹15-25 lakhs and 3-4 months into your home's interior design. One forgotten detail, one missed decision, one overlooked step can cost thousands and weeks of delay.

After managing 450+ projects at Divya Jain Interiors, we've created this comprehensive checklist—everything you need to do before hiring a designer, during execution, and after project completion.

Bookmark this page. You'll reference it dozens of times over the next few months.


PHASE 1: Before Starting (2-3 Months Before)

Financial Planning

Determine total budget

     Include 10-15% contingency (unexpected costs always arise)

     Factor in: Interior + Civil work + Appliances + Contingency

     See realistic budgeting in our 3BHK cost guide

Understand financing options

     Home improvement loan? (12-14% interest typically)

     Personal loan?

     Savings?

     Mix of above?

Create budget allocation

     Kitchen: 20-25% of interior budget

     Master bedroom: 15-20%

     Living areas: 15-20%

     Other bedrooms: 15-20%

     Bathrooms & doors: 10-15%

     Electrical & false ceiling: 10-15%

Confirm payment capacity

     Can you make staged payments? (typically 5 stages)

     Initial deposit ready? (usually 10-15% to start design)


Timeline Planning

Decide project start date

     Avoid starting during: Diwali (Oct-Nov), major festivals

     Best months in Pune: Jan-May, Sep-Dec

     Consider: When can you vacate? When do you need to move in?

Plan accommodation

     Full interior: Must vacate completely (60-90 days)

     Renovation: May live in apartment (some areas at a time)

     Where will you stay? (rental, family, hotel?)

Calculate total timeline

     Design finalization: 4-6 weeks

     Material procurement: 2-3 weeks

     Execution: 60-90 days (3BHK turnkey)

     Buffer: Add 2-3 weeks for unforeseen delays

     Total: 4-5 months from first meeting to move-in

See detailed timeline in our week-by-week process guide.


Research & Planning

Collect inspiration

     Pinterest boards (create separate boards: Kitchen, Bedrooms, Living, etc.)

     Instagram saves

     Magazine clippings

     Photos from friends' homes

     Note what you DON'T like (equally important)

Understand your home

     Get architectural drawing (floor plan with dimensions)

     Note: Load-bearing walls (can't remove)

     Identify: Wet areas, electrical panel location, water supply points

     Check: Society rules and restrictions

List functional requirements

     How many people's clothes in each wardrobe?

     Kitchen: How many utensils, appliances, groceries to store?

     Work from home? Need dedicated office?

     Exercise at home? Need space for equipment?

     Hobbies requiring space? (music, art, reading)

Decide on service model

     Design Only? Design + Supervision? Turnkey?

     See comparison in our service models guide


Designer Selection

Shortlist 3-5 designers

     Local Pune designers (understand monsoon, local challenges)

     Check Google reviews (minimum 20+ reviews, 4+ rating)

     View Instagram/website portfolio

     Verify: Years in business, number of projects completed

Schedule consultations

     Meet at their office/studio (see their setup)

     Ask to visit 1-2 completed projects (essential)

     Bring: Floor plan, inspiration images, budget range

Questions to ask each designer

     How many Pune projects completed?

     Can we visit completed projects? (Red flag if no)

     What's your typical timeline? (accountability)

     Payment schedule? (tied to milestones)

     Warranty terms? (2 years workmanship minimum)

     What happens if you delay? (penalty clause?)

     Itemized quote or lump sum? (itemized better)

Compare quotes properly

     Don't just look at total price

     Compare: Plywood grade, hardware brand, warranty terms

     What's included vs excluded?

     See common mistakes in our mistakes guide


Legal & Documentation

Review apartment documents

     Ownership papers (clear title?)

     Society rules (work timings, permissions needed?)

     Building age and condition

     Any pending society dues?

Check society requirements

     Work hours allowed? (typically 9 AM - 6 PM)

     Sundays allowed?

     Deposit required? (₹5,000-15,000 typical, refundable)

     Permissions needed for structural work?

Verify contractor requirements

     Police verification needed for workers?

     Insurance requirements?

     Safety deposit?


PHASE 2: Design Development (4-6 Weeks)

Initial Stage

Finalize designer and sign contract

     Review contract thoroughly (take 48 hours)

     Clarify: Scope, timeline, payment, warranties

     Get everything in writing

Pay initial deposit

     Typically 10-15% to start design work

     Get proper receipt with GST

Schedule site measurement

     Be present during measurement (point out specifics)

     Discuss: Problem areas, structural issues, concerns

Share detailed requirements

     Every bedroom: Whose room, storage needs, work area needed?

     Kitchen: Cooking style, appliances owned, family size

     Living areas: Entertaining frequency, TV size, storage needs

     Bathrooms: Tub or shower? Storage requirements?


Design Review Stage

Review 2D layouts (multiple options)

     Does furniture placement feel right?

     Is circulation smooth? (3 feet minimum walkways)

     Are doors obstructed?

     Power points conveniently located?

Mark furniture positions physically

     Use tape on apartment floor

     Sit in rooms, walk through

     Visualize daily life

     Adjust before finalizing

Review 3D visualizations

     Do colors work together?

     Is lighting adequate?

     Does aesthetic match your vision?

     Will this look good in 5 years? (avoid trendy over timeless)

Approve technical drawings

     Carpentry drawings (dimensions, materials specified)

     Electrical layout (point locations, switch positions)

     Plumbing layout (kitchen, bathrooms)

     False ceiling plan (lighting positions)


Material Selection

Visit showrooms with designer

     See physical samples (colors look different than screens)

     Touch materials (laminate textures, hardware weight)

     Operate hardware (soft-close feel, drawer smoothness)

Finalize all materials

     Plywood grade (BWR 710 minimum for Pune)

     Laminate/veneer selections (with codes)

     Hardware brand and finishes

     Countertop material and color

     Paint colors (in daylight and artificial light)

     Flooring (if changing)

     See material considerations in our monsoon-proof guide

Get final itemized quote

     Every item listed with specifications

     Material grades mentioned

     Brand names specified

     Warranties stated

     Payment schedule clear

Approve and sign off

     This is the point of no return

     Changes after this = additional costs

     Take time, be 100% sure


PHASE 3: Pre-Execution (2-3 Weeks)

Administrative Tasks

Complete all payments as per schedule

     First milestone (typically after design approval)

     Keep receipts organized

Obtain society permissions

     Submit required documents

     Pay society deposit if needed

     Get written approval for work

Arrange temporary accommodation

     If vacating: Book 3 months minimum

     Keep some overlap (projects can extend)

Set up communication channels

     WhatsApp group with designer/project manager

     Schedule: Weekly calls (day/time fixed)

     Emergency contact numbers


Site Preparation

Clear apartment completely

     Remove all furniture (if fresh interior)

     Store items safely

     Remove curtains, wall decor, everything

Disconnect services temporarily

     Gas connection (if kitchen relocation)

     Internet/cable (if point changes)

     Keep electricity and water on

Protect existing fixtures

     Items not being replaced (tiles, fixtures)

     Windows and doors

     Bathroom fittings staying

Provide site access

     Duplicate keys to contractor

     Society gate pass arranged

     Access timings coordinated


PHASE 4: During Execution (60-90 Days)

Weekly Tasks

Attend weekly progress calls (15 minutes)

     What was completed this week?

     What's planned for next week?

     Any issues or delays?

     Any decisions needed from you?

Review photo updates

     Daily photos via WhatsApp (good designers send these)

     Compare against timeline

     Note any concerns early

Schedule site visits

     Week 4: Mid-carpentry stage

     Week 8: Before painting begins

     Week 11: Pre-final inspection

     More if you're in Pune and available


Decision Points

Material arrivals

     Inspect quality when delivered

     Match against specifications

     Verify quantities

Work stage approvals

     Carpentry framework (before shutters)

     Electrical rough-in (before plastering)

     Paint primer (before final coats)

     Hardware installation (before final fixing)

Change requests

     Avoid mid-execution changes (costly)

     If absolutely necessary: Get written quote first

     Document reason (learning for future)


Payment Milestones

Stage payments as per contract

     Typically: Material delivery (50%), Hardware & finish (35%), Paint (10%), Final (5%)

     Only pay after verifying work completion

     Keep 5-10% for final handover

Keep payment records

     All receipts and invoices

     Track against contract

     Note any additional charges


Quality Checks

Monitor key quality points

     Plywood edges sealed (moisture protection)

     Hardware operating smoothly

     Paint finish even and smooth

     Shutters aligned properly

     No visible screws or joints

     Drawers sliding smoothly

Document issues immediately

     Photos of problems

     WhatsApp to project manager

     Note date and location

     Track resolution


PHASE 5: Completion (Week 12-13)

Pre-Final Inspection

Room-by-room walkthrough

     Test every drawer, shutter, door

     Check all electrical points

     Operate all hardware

     Look for scratches, dents, misalignment

     Note: Even minor issues (they'll compound)

Create punch list

     Document everything needing fix/adjustment

     Photos of each issue

     Give timeline for fixes (48-72 hours typical)

Verify against contract

     Is everything delivered as promised?

     Any missing items?

     Material grades correct?


Final Handover

Final walkthrough after fixes

     Verify punch list items completed

     Check cleaning done thoroughly

     Everything functioning?

Collect documentation

     Material warranties (plywood, hardware)

     Appliance manuals and warranties

     Paint color codes (for future touch-ups)

     Vendor contact list (for future purchases)

     Maintenance instructions

     Workmanship warranty certificate

Make final payment

     Only after 100% satisfaction

     Get proper paid invoice

     Get warranty certificate

Take handover photos/videos

     Document condition at handover

     Useful for warranty claims later

     Before-after comparison for social media!


PHASE 6: Post-Handover (First 30 Days)

Immediate Actions

Deep clean again (your standards)

     Construction dust settles for 2-3 days

     Clean all wardrobes inside

     Wipe all surfaces

Install remaining items

     Curtains and blinds

     Light fixtures (if not done)

     Decorative items

     Plants and accessories

Arrange furniture and decor

     Move in gradually (not all at once)

     Live in space before buying more furniture

     See what's actually needed vs planned


First Week

Test everything daily

     Open every drawer multiple times

     Operate all shutters

     Use kitchen extensively

     Check for any issues

Note any problems

     Sticky drawers

     Misaligned shutters

     Paint touch-ups needed

     Hardware adjustments

Report issues immediately

     Within first week = easy fixes

     After 30 days = may fall outside warranty


First Month

Schedule day 7, 15, and 30 check-ins

     Good designers do this automatically

     Discuss any issues observed

     Get maintenance tips

Conduct post-monsoon check (if applicable)

     Any moisture issues?

     Wood swelling?

     Mold or odors?

     Address immediately

Leave online review

     If satisfied: Help others find good designer

     If issues: Give designer chance to fix first

     Fair, honest review helps everyone


PHASE 7: Long-Term (Years 1-2)

Maintenance Checklist

Monthly

     Wipe down kitchen cabinets (prevent buildup)

     Clean hardware with dry cloth

     Check for loose screws/fittings

Every 6 Months

     Deep clean all wardrobes (empty and wipe)

     Check hinges and channels (lubricate if needed)

     Touch up paint scratches

     Check silicon sealing (kitchen, bathrooms)

Yearly

     Professional anti-fungal treatment (₹3,000-5,000)

     Silicon re-sealing where needed

     Hardware servicing (if operating roughly)

     Paint touch-ups (high-traffic areas)

After Each Monsoon

     Inspect all woodwork near external walls

     Check for moisture damage early

     Address issues before they spread

     See prevention tips in our monsoon guide


Warranty Management

Keep warranty documents organized

     Workmanship: 2 years (typically)

     Plywood: 5-20 years (depending on grade)

     Hardware: 10-25 years (depending on brand)

     Paint: 5-7 years (manufacturer warranty)

Document any issues

     Photos with dates

     Description of problem

     When it started

Contact designer for warranty claims

     Within warranty period

     Provide documentation

     Give reasonable time to address

Annual maintenance visit (if offered)

     Some designers include one annual visit

     Inspection and minor adjustments

     Builds long-term relationship


Special Considerations for Pune

Monsoon-Specific Checklist

Before monsoon (May-June)

     Check all window seals

     Ensure exhaust fans working

     Apply furniture wax/polish

     Use silica gel packets in wardrobes

During monsoon (June-September)

     Run exhaust fans daily (even if not showering)

     Open wardrobes weekly for ventilation

     Wipe kitchen surfaces daily

     Check for black spots (early mold signs)

Post-monsoon (October)

     Deep clean everything

     Inspect for any damage

     Air out all enclosed spaces

     Address issues before they worsen


Society-Specific Checklist

Before starting work

     Verify work timings allowed

     Confirm material delivery logistics

     Arrange parking for contractor vehicles

     Inform neighbors (courtesy)

During work

     Stick to allowed timings

     Minimize common area disruption

     Clean up daily

     Address neighbor complaints promptly

After completion

     Clean common areas used

     Collect society deposit back

     Get No Objection Certificate (if required)

     Thank society office and security


Red Flags During Process

🚩 Stop and address if you notice:

     Designer not responding to calls/messages (2+ days)

     Work quality suddenly declining

     Materials different from approved samples

     Timeline slipping with no explanation

     Hidden costs appearing

     Contractor behavior unprofessional

     Safety issues at site

Action: Document issue, escalate to senior management, withhold payment if needed.


Your Master Checklist Summary

Before Starting (2-3 months):

     Budget and financing sorted

     Timeline planned

     Designer selected and contracted

     Materials and designs finalized

During Execution (60-90 days):

     Weekly check-ins done

     Quality monitored

     Payments on schedule

     Issues addressed promptly

After Completion (30+ days):

     Thorough inspection done

     Documentation collected

     Issues within warranty reported

     Regular maintenance followed

Print this checklist. Keep in project folder. Check off as you go.


Ready to Start Your Project Right?

This checklist represents 450+ projects worth of learning—everything we wish every client knew before starting.

Have it with you during your consultation, and we'll walk through it together.

Schedule Your Free Consultation:

📞 Call: +91-8959070757 / +91-8390707573

💬 WhatsApp: Click to message

🌐 Visit: www.divyajaininteriors.com

During consultation:

     We'll review this checklist together

     Customize it for your specific project

     Identify any additional steps for your situation

     Give you a project timeline with milestone dates

     Provide realistic budget and expectations

Preparation prevents problems. Let's get it right from day one.